South East Coalville (Phase 2)

Gam Civil Engineering was appointed for the installation of new foul water drainage systems, including an SFA foul water pumping station with emergency storage tanks, and installation of PCC box culvert structures.

Project Scope for South East Coalville (Phase 2):

· 1450m of foul water drainage at depths between 1.5m and 5m deep, and pipe size ranges between 150mm and 300mm, and all associated manholes.

· 2000m of storm water drainage at depth ranges between 1m and 6m deep, with pipe sizes between 150mm and 675mm, and all associated manholes.

· Installation of 34m of 6.500mm x 3.200mm of PCC box culverts and headwalls.

· Installation of SFA foul water pumping station with a 2400mm diameter wet well at a depth of 6.5m. Including four 17.5m x 2.6mm diameter SPEL emergency storage tanks at a depth of 4m.

· Provision of site engineering and supervision.

Get in touch